The Project
- Asbestos removal
- Remove oil tank, oil boiler and associated mechanical and electrical installation
- Network gas connection, associated civils.
- 2no. 190kW high efficiency modulating and condensing gas boiler
- New flues
- Gas train, circulation pumps, pressurisation unit, valves and pipework
- New MCC and BMS panel, associated controls
- Pipe and valve lagging
- Boiler house painting, new doors, etc.